Short answer. Yes. Port Coquitlam requires a Sign Permit to construct, alter or repair a sign, and every sign is inspected after the permit is issued. Signs not specifically permitted by the bylaw are prohibited.
What needs a permit
- A Sign Permit is required to construct, alter or repair a sign.
- No sign may be erected, placed, displayed, altered or moved except as the Sign Bylaw allows (section 2.1).
- Signs that are not specifically permitted in the bylaw are prohibited.
Key rules
- All measurements in the bylaw are metric.
- Where the Sign Bylaw and the Zoning Bylaw conflict, the Zoning Bylaw prevails.
- After a permit is issued, the City inspects every sign against the approved plans and location.
How to apply
- Submit the Sign Permit application with fees. The fee is based on the sign's construction value, with a minimum permit fee of $120.
- Include a Letter of Consent from the property owner and scaled drawings showing the sign's size and location on the building or property.
- A $500 security deposit is required for a sign weighing 25 kg (55 lb) or more. Credit cards are not accepted for the deposit.
- Planning Division, 200-2564 Shaughnessy Street. Phone 604-927-5442, [email protected].
Lit signs and electrical approval
The City of Port Coquitlam sign permit covers size, placement and appearance. Electrical safety is a separate approval. In BC, the Electrical Safety Regulation does not allow electrical equipment to be used or sold unless it carries an accredited certification mark. For an electric sign the Canadian standard is CSA C22.2 No. 207, and the mark goes on the finished sign. The connection is made by a licensed electrician under an electrical permit. More in our guide to cUL certified signs.
Sources
This page summarizes official City of Port Coquitlam sources. Bylaws and fees change, so confirm with the municipality before you order or install a sign.